Goodwood School Carpark

Goodwood School Board of Trustees

Goodwood School Board of Trustees engaged CCS to construct an asphalt concrete carpark, containing 42 parking spaces at the school. The original site was green fields, so the construction included clearing, topsoil stripping, minor earthworks, new pavement, surfacing and line marking. The works included drainage and the construction of a soakage trench. On completion, additional works were added to the contract, comprising new concrete footpaths and the upgrade of an adjacent access track.

The contract was completed during the school term, meaning that site safety was a priority. Liaison with the school was of great importance to ensure the success of the project. The school and the community were very impressed with the project, providing feedback with how thrilled they were with the level of professionalism throughout the build.